Brick work completed for all flats. |
 |
Inner plastering completed for all flats. |
 |
Electrical wall chasing and conduits laying completed for all flats. |
 |
Elevation column design work in progress(15% completed). |
 |
West elevation brick work in progress.(80% completed). |
 |
Elevation floating columns concrete in progress (80% completed). |
 |
Plumbing work completed for 16 flats. |
 |
Water proofing completed for 16 flats. |
 |
2 coats of ceiling putty and 1 coat of wall putty completed for 30 flats. |
 |
Door frame fixing completed for 50 flats. |
 |
Model Flat in progress(85% completed). |
 |
Tiles laying in progress for 1st floor bathrooms. |
 |
Outer plastering in progress. |